Each bridge deck, prefabricated in Austria, comes in five pieces, but they are welded together before it is launched. Also, 10 hanger cables had been replaced with the 11th and 12th cables being worked on. There are 40 hanger cables in all, each of which comes in two pairs.
Even though the old deck was made of concrete on steel, Mr Baah said the new bridge would be of asphalt on steel as the concrete was much heavier. The two walkways on each side of the bridge would, however, be made of concrete on steel. A new tollbooth would now be sited about 1.2 kilometres from the bridge. A new feature, an inspection platform, would now be fixed under the bridge. The inspection platform, according to Mr Baah, would work hydraulically and could be operated at sections to detect any defects that might develop on the bridge. He said the lack of this feature on the old bridge made such detections rather difficult. Also, an improvised lift fabricated at the project site enables some of the artisans to move up the arch and work on the replacement of the hanger cables. Under the contract, the government is required to give tax exemptions to the contractor but the Project Manager, Mr Paul Herrmann, said the company was yet to receive the Tax Exemption Certificate. "This exemption, which we don't have, is one of the challenges we are facing, causing us expenses we are not prepared for," he stated. According to him, the company had as at October last year paid more than GH¢100,000 in taxes to the state. Meanwhile, the two ferries which were launched prior to the closure of the bridge are still operational and the Ghana Highway Authority (GHA) has completed construction works on the Akuse-Old Akrade road which provides access from Akuse junction through the Volta River Authority ( VRA) Dam. |
Categories
All
Home PageNews Archives
July 2021
Did you know?
Marburg virus and Ebola virus are the SAME..! Read Here! GhanaWeb-News.com
|